Receiving-departuring yard: 3 tracks - 1,520 mm gauge 3 tracks - 1,435 mm gauge
Customs control zone: 3 tracks - 1,520 mm gauge 2 tracks - 1,435 mm gauge
Bridge
Crossing
Total length: 2,209 m (Russian section: 306 m)
Span layout: 60+108+132 m (Russian side)
The project complies with requirements for preserving the Amur fairway and maintaining the state border, approved by the joint Russia-China working group Future perspective: growth to 22,4 million tons via modernization of the Birobidzhan-Leninsk section and construction of new terminal infrastructure
On the Chinese
side
Tongjiang-North station
Transshipment yard: 5 tracks - 1,520 mm 5 tracks - 1,435 mm
Inspection yard: 2 tracks - 1,520 mm 2 tracks - 1,435 mm
Coal, ore, and timber transshipment is performed using grab and specialized cranes